Onward and Upward

Posted By on 18th March 2016

On Wednesday we had a full compliment of builders, a delivery of bricks and the truss man came!

No we haven’t suffered a catastrophic medical emergency, it was the roof truss man who came to measure up for the roof.

Adrian and Tony finished building the inner wall and then started on the 8 internal brick piers which will provide strength to the structure and support for the roof trusses.

Here you can see them building ‘Morgan’ and ‘Brosnan’, (see what we did there?!) while Brett and Peter look on.

134

Yesterday the scaffolding team arrived and after about 90 minutes we had this.

135

Never having had scaffolding before I was surprised at the scale of the structure for such a small building, but I suppose safety is the main concern and it certainly looks very safe. I’m even considering going up it myself!