More Maths

Posted By on 24th March 2016

Monday was a bit of a slow burn, Brett carried lots of bricks onto the scaffolding platforms whilst Peter and Adrian struggled with the finer points of the second lot of step. These are now testing his geometry skills, so once again lessons long forgotten had to be rediscovered.

Tuesday and Wednesday saw better progress with the garage walls and piers being built up to full height

138

ready for the roof trusses, and more progress was made on the second lot of steps which are now taking shape after the head scratching of Monday.

137

Work has finished now for the Easter holidays, but on Tuesday Adrian will be bringing a micro-digger, whatever one of those is, can’t wait!!